2.2 General Description of the Project
2.3 Construction Programme and Activities
2.5 Status of Environmental Licences, Notification and Permits
3 Environmental Monitoring Requirement
3.1 Construction Dust Monitoring
4 IMPLEMENTATION status of ENVIRONMENTAL mitigation measures
5.1 Construction Dust Monitoring
6 Environmental site inspection and audit
7 Environmental non-CONFORMANCE
7.1 Summary of Monitoring Exceedances
7.2 Summary of Environmental Non-Compliance
8.1 Construction Programme for the Next Three Months
8.2 Key Issues for the Coming Month
8.3 Monitoring Schedule for the Next Month
9 Conclusion and Recommendation
Table 2.1 Summary of Major Construction Activities in the Reporting Period
Table 2.2 Contact Information of Key Personnel
Table 2.3 Status of Environmental Licenses, Notification and Permits
Table 3.1 Action and Limit Levels for 1-hour TSP
Table 3.2 Air Quality Monitoring Equipment
Table 3.3 Locations of Construction Dust Monitoring Station
Table 3.4 Action and Limit Levels for Water Quality
Table 3.5 Water Quality Monitoring Equipment
Table 3.6 Analytical Methods to be applied to Water Quality Samples
Table 3.7 Locations of Water Quality Monitoring Stations
Table 5.1 Summary of 1-hour TSP Monitoring Result in the Reporting Period
Table 5.2 Summary of Water Quality Monitoring Results in the Reporting Period
Table 5.3 Quantities of Waste Generated and Disposal Location in the Reporting Period
Table 6.1 Observation and Recommendations of Site Audit
Table 7.1 Summary of Exceedance
Table 7.2 Summary of Environmental Complaints, Summon and Successful Prosecution
Table 8.1 Major Construction for the Next Three Month.
Figure 2.1 |
Site Layout Plan |
Figure 3.1 |
Locations of Construction Dust Monitoring Stations |
Figure 3.2 |
Locations of Water Quality Monitoring Stations |
Appendix A |
Tentative Construction Programme |
Appendix B |
Project Organization Structure |
Appendix C |
Project Implementation Schedule of Environmental Mitigation Measures |
Appendix D |
Calibration Certificates of Equipment and Certificates of HOKLAS Laboratory |
Appendix E |
Monitoring Schedules |
Appendix F |
Air Quality Monitoring Results and their Graphical Presentations |
Appendix G |
Wind Speed and Direction from Hong Kong Observatory |
APPENDIX H |
Event and Action Plan |
APPENDIX I |
Water Quality Monitoring Results and their Graphical Presentation |
APPENDIX J |
Monthly Summary Waste Flow Table |
APPENDIX K |
Cumulative Statistics on Complaints, Notification of Summons and Successful Prosecutions |
The Environmental Impact Assessment (EIA) Report and its Environmental Monitoring and Audit (EM&A) Manual (Register No. AEIAR-240/2022) for HSKEPP was approved on 19 October 2022, with an Environmental Permit (EP) granted on 19 October 2022 (EP No. EP-608/2022) under the Environmental Impact Assessment Ordinance (EIAO).
The construction was commenced on 6 September 2024. This is the 1st EM&A report documents the findings of EM&A works conducted during the period from 6 to 30 September 2024.
EM&A Activities Summary
A summary of the EM&A activities in this reporting month is listed below:
EM&A Activities |
Date |
Air Quality Monitoring |
7, 13, 19, 25 and 30 September 2024 |
Water Quality Monitoring |
7, 9, 11, 13, 16, 19, 21, 23, 25, 27 and 30 September 2024 |
Environmental Site Inspection |
12, 16 and 26 September 2024 |
Breaches of Action and Limit Levels for Air Quality
No exceedance of the Action / Limit Level of 1-hour Total Suspended Particulates (TSP) was recorded in the reporting month. Details are provided in Appendix F.
Breaches of Action and Limit Levels for Water Quality
No exceedance of the Action / Limit Level of water quality monitoring was recorded in the reporting month. Details are provided in Appendix I.
Complaint, Notification of Summons and Successful Prosecution
No environmental complaint, notification of summons and successful prosecution were received in the reporting month.
Reporting Changes
There was no reporting change in the reporting month.
Future Key Issues
Key issues to be considered in the next three months included the following.
Site |
Construction Activities |
Contract No. DC/2023/15 Site Formation Works for Hung Shui Kiu Effluent Polishing Plant Phase 1 |
- Construction of Hoarding - Ground Investigation Works - Tree Felling Works - Demolition Works |
Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, water quality and waste management.
WSP (Asia) Limited (WSP) was appointed by Drainage Services Department (DSD) as the Environmental Team (ET) to undertake the Environmental Monitoring and Audit (EM&A) programme during construction phase of the Hung Shui Kiu Effluent Polishing Plant (HSKEPP) (hereinafter referred to as “the Project”).
1.1.1 The Environmental Monitoring and Audit (EM&A) programme for the Project commenced on 6 September 2024. This is the 1st EM&A Report for the Project which summarises the impact monitoring results and audit findings for the Project during the period from 6 to 30 September 2024.
1.2.1 This monthly EM&A Report is organized as follows:
(a) Section 1: Introduction
(b) Section 2: Project Information
(c) Section 3: Environmental Monitoring Requirement
(d) Section 4: Implementation Status of Environmental Mitigation Measures
(e) Section 5: Monitoring Results
(f) Section 6: Environmental Site Inspection and Audit
(g) Section 7: Environmental Non-conformance
(h) Section 8: Future Key Issues
(i) Section 9: Conclusions and Recommendations
2.1.1 The Hung Shui Kiu Effluent Polishing Plant (HSKEPP) (the Project) which is located in the north-western side of the Hung Shiu Kiu / Ha Tsuen New Development Area (HSK/HT NDA). It is designed to provide reliable, adequate and quality sewage treatment and sewage effluent disposal for the sewage collected from the new developments within the HSK/HT NDA and other developments on the North West New Territories (NWNT).
2.1.2 An Environmental Impact Assessment (EIA) study for the Project was conducted in accordance with EIA Study Brief No. ESB- 312/2019. The EIA Report and Environmental Monitoring and Audit (EM&A) Manual (Register No. AEIAR – 240/2022) were approved on 19 October 2022 under the Environmental Impact Assessment Ordinance (EIAO), with an Environmental Permit (EP) granted on 19 October 2022 (EP No. EP-608/2022).
2.1.3 According to the approved EM&A Manual of HSKEPP, the EM&A monitoring for the Project includes air quality monitoring and water quality monitoring. Baseline dust and water quality monitoring for HSKEPP was carried out within 24 June 2024 and 20 July 2024.
2.2.1 The key elements of this Project comprise below:
(a) Demolition of existing structures and buildings within San Wai Preliminary Treatment Works (SWPTW) for construction of HSKEPP facilities;
(b) Construction of a sewage treatment plant with a maximum capacity of Average Dry Weather Flow (ADWF) up to 90,000 m3/day;
(c) Construction of sludge treatment facilities for treating sludge generated from Hung Shui Kiu (HSK) Effluent Polishing Plant (EPP) and additional sludge generated from the San Wai Sewage Treatment Works (STW) and other nearby STWs;
(d) Construction of facilities for receiving and co-digesting pre-treated food or organic wastes;
(e) Construction of effluent discharge pipe connecting to the existing discharge tunnel of San Wai STW; and
(f) Associated ancillary works.
2.2.2 The layout plan of the Project is shown in Figure 2.1.
2.3.1 The major construction activities undertaken in the reporting month are summarised below:
Table 2.1 Summary of Major Construction Activities in the Reporting Period
Site |
Construction Activities |
Contract No. DC/2023/15 Site Formation Works for Hung Shui Kiu Effluent Polishing Plant Phase 1 |
- Site Clearance - Pre-conditional Surveying - Ground Investigation Works |
2.3.2 The tentative construction programme is presented in Appendix A.
2.4.1 The project organization structure is shown in Appendix B. The key personnel contact names and numbers for the Project are summarized in Table 2.2.
Table 2.2 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
DSD |
Project Proponent |
Engr/6 (Harbour Area Treatment Scheme) |
Mr. Gabriel Lau |
2159 3410 |
AECOM |
Engineer’s Representative |
Associate |
Ms. Yanning Zhang |
5315 1068 |
ERM |
Independent Environmental Checker (IEC) |
Independent Environmental Checker |
Ms. Mandy To |
2271 3313 |
Adrian Construction Limited |
Contractor |
Environmental Officer |
Mr. Tak-chi Tsoi |
9226 6337 |
WSP |
Environmental Team (ET) |
ET Leader |
Mr. Squall Lam |
2579 8841 |
2.5.1 Relevant environmental licenses, permits and/or notifications on environmental protection for the Project and valid in the reporting month are summarized in Table 2.3.
Table 2.3 Status of Environmental Licenses, Notification and Permits
Permit / License No. / Notification/ Reference No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Environmental Permit |
||||
EP-608/2022 |
19 Oct 2022 |
- |
Valid |
EP-608/2022 |
Wastewater Discharge License |
||||
10009181 (Reference No.) |
- |
- |
- |
Date of Application: 13th September 2024 |
Chemical Waste Producer Registration |
||||
5213-511-A3217-01 |
25 Jul 2024 |
- |
Valid |
- |
Billing Account for Construction Waste Disposal |
||||
7051624 |
29 Jul 2024 |
- |
Valid |
- |
Notification Under Air Pollution Control (Construction Dust) Regulation |
||||
- |
- |
- |
- |
Notification has been submitted to EPD on 5 July 2024 |
3.1.1 In accordance with the approved EM&A Manual, 1-hour Total Suspended Particulates (TSP) level at the designated air quality monitoring station is required. Impact 1-hour TSP monitoring should be carried out for at least three times in every six-days at the designated monitoring stations. The Action and Limit Level of the air quality monitoring is provided in Table 3.1.
Table 3.1 Action and Limit Levels for 1-hour TSP
ID |
Location |
Action Level |
Limit Level |
AM1 |
Tseung Kong Wai |
263.0 mg/m3 |
500 mg/m3 |
AM2 |
Farm House |
260.6 mg/m3 |
500 mg/m3 |
AM3 |
Planned Port Back-up, Storage and Workshop |
263.4 mg/m3 |
500 mg/m3 |
3.1.2 1-hour TSP air quality monitoring was performed using portable direct reading dust meter located at the designated monitoring stations. Portable direct reading dust meters used for the monitoring were proven to IEC to be capable of achieving comparable result as that of the dust meter and thus were used for sampling. The portable direct reading dust meters meet all the requirements of the EM&A Manual. Brand and model of the equipment is given in Table 3.2. Their latest calibration certificates of the portable direct reading dust meter are provided in Appendix D.
Table 3.2 Air Quality Monitoring Equipment
Equipment |
Brand and Model |
Portable
direct reading dust meter |
TSI Handheld TSP Meter (Model No. AM520; S/N: 5201735004) |
TSI Handheld TSP Meter (Model No. AM520; S/N: 5201735006) |
|
TSI Handheld TSP Meter (Model No. AM520; S/N: 5202345003) |
3.1.3 The monitoring station for construction dust monitoring pertinent to the Project has been identified based on the approved EM&A Manual for HSKEPP of the Project. The location of the construction dust monitoring stations is summarised in Table 3.3 and shown in Figure 3.1.
Table 3.3 Locations of Construction Dust Monitoring Station
Monitoring Location ID(1) |
Dust Monitoring Location |
AM1 |
Tseung Kong Wai |
AM2 |
Farm House |
AM3 |
Planned Port Back-up, Storage and Workshop |
Note:
(1) 1-hour TSP impact monitoring should be conducted at the monitoring stations when there are Project-related major construction activities including site formation and piling works being undertaken within a radius of 500m from the monitoring stations.
3.1.4 The 1-hour TSP was sampled by drawing air into the portable dust monitor where particular concentrations were measured instantaneously with an in-built silicon detector sensing light scattered by the particulates in the sampled air. Continuous TSP levels were indicated and logged by a built-in data logger compatible with Windows based program to facilitate data collection, analysis and reporting.
Field Monitoring
3.1.5 The measuring procedures of the 1-hour dust meter was undertaken in accordance with the Manufacturer’s Instruction Manual as follows:
(a) Power on the meter
(b) Check the data and time
(c) Check the battery and make sure it is good enough to complete the sampling
(d) Select the “Calibration” from the menu
(e) Plug in the zero calibration filter to the meter
(f) Select the “Zero Cal” and run it
(g) Back to main menu and select the “Run Mode/Manual Mode”
(h) Press “Enter” to start the sampling
(i) When sampling is completed, press the “Enter” to stop the sampling
(j) Back to the main menu and select the “Data”
(k) Select the “Statistic” and read back the last memory record
3.1.6 Adoption of the wind data from the existing automatic wind station, i.e. Lau Fau Shan, operated by Hong Kong Observatory (HKO) rather than setting up wind data monitoring equipment is based on the following justifications:
· Lau Fan Shan automatic wind station is located in the vicinity of the designated monitoring locations. This Automatic wind station (22°28'08", 113°59'01") is located at the north of the Project and the anemometer is set up at 31m above mean sea level. It is clear of obstructions or turbulence caused by the buildings;
· This automatic wind station was considered as the closest wind station to the Project that could provide representative wind data in Hung Shui Kiu areas; and
· Wind data collected by HKO was considered as a reliable data source for the wind data, it is widely used in many EM&A Projects (e.g. Expansion of Hong Kong International Airport into a Three-runway System, Siu Ho Wan Station and Siu Ho Wan Depot Replanning Works – Advance Construction Works). The dataset is more accurate and reliable that could be downloaded periodically with real-timed data logger.
3.1.7 The data collected from Lau Fau Shan was used to check the wind speed and wind direction. Details of the collected wind data were presented in Appendix G.
Maintenance and Calibration
3.1.8 The portable direct reading dust meter is calibrated every year against high volume sampler (HVS) to check the validity and accuracy of the results measured by direct reading method.
3.1.9 All monitoring data will be handled by the ET’s in-house data recording and management system. The monitoring data recorded in the equipment will be downloaded directly from the equipment at the end of each monitoring day. The downloaded monitoring data will input into a computerized database maintained by the ET. The laboratory results will be input directly into the computerized database and checked by personnel other than those who input the data.
3.1.10 For monitoring parameters that require laboratory analysis, the local laboratory shall follow the QA/QC requirements as set out under the HOKLAS scheme for the relevant laboratory tests.
3.1.11 The schedule for dust monitoring conducted in September 2024 is provided in Appendix E.
3.2.1 In accordance with the approved EM&A Manual and EP, baseline water quality monitoring was undertaken to establish the baseline water quality levels at the designated monitoring stations. The stream water quality baseline monitoring was conducted 3 days per week for at least 4 weeks prior to the commencement of the works, with sampling/measurement at all designated monitoring stations including control station as specified in Table 3.7.
3.2.2 Measurements at the C1 and M1 stations for construction stage at were taken. Water depths, namely, 1m below water surface, mid-depth and 1m above sea/river bed, except where the water depth less that 6m, in which case the mid-depth station may be omitted. Should the water depth be less than 3m, only the mid-depth station will be monitored. The Action and Limit Level of the water monitoring is provided in Table 3.4.
Table 3.4 Action and Limit Levels for Water Quality
Parameter |
Station M1 |
|
Action Level |
Limit Level |
|
DO in mg/L |
3.8 |
3.7 |
Turbidity in NTU |
17.2 OR 120% of upstream control station(s) at the same tide of the same day, whichever is higher |
17.7 OR 130% of upstream control station(s) at the same tide of the same day, whichever is higher |
SS in mg/L |
25 OR 120% of upstream control station(s) at the same tide of the same day, whichever is higher |
26 OR 130% of upstream control station(s) at the same tide of the same day, whichever is higher |
3.2.3 Dissolved Oxygen (DO), Salinity, Temperature, pH, and Turbidity should be monitored at designated water quality monitoring stations. All parameters should be measured in-situ whereas suspended solids (SS) should be determined by the laboratory. DO should be presented in mg/L and in % saturation.
3.2.4 Other relevant data should also be recorded, including monitoring location / position, time, weather conditions and any special phenomena or work underway at the construction site during the monitoring.
3.2.5 Based on the approved EM&A Manual, the monitoring equipment in Table 3.5 were used for the in-situ measurement of water quality. A copy of the calibration certificates for the water quality monitoring equipment are provided in Appendix D.
Table 3.5 Water Quality Monitoring Equipment
Equipment |
Model |
DO and Temperature Meter, Salinity Meter, pH meter and Turbidimeter |
YSI ProDSS Multi Parameters |
Serial Number |
1. 16H104233 2. 21K101469 3. 21G105356 |
Water Depth Sensor |
Xyorca XY-453 (S/N: OA35000025) |
Water Sampler |
1120-1180 Vertical AlphaTM Bottles |
Dissolved Oxygen and Temperature Measuring Instrument
3.2.6 The instrument is a portable and weatherproof DO measuring instrument complete with cable and sensor and use a DC power source. The equipment is capable of measuring:
· a DO-level in the range of 0 - 20 mg/L and 0 - 200% saturation; and
· a temperature of 0 - 45 degree Celsius
3.2.7 It has a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables should be available for replacement where necessary. (For example, YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).
3.2.8 Salinity compensation was not built-in to the DO equipment, in-situ salinity measured to calibrate the DO equipment prior to each DO measurement.
Turbidity Measuring Instrument
3.2.9 Turbidity measured in-situ by the nephelometric method. The instrument is portable and weatherproof using a DC power source complete with cable, sensor and comprehensive operation manuals. It has a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU (for example, Hach model 2100P or an approved similar instrument). The cable is not less than 25m in length. The meter calibrated in order to establish the relationship between NTU units and the levels of suspended solids. The turbidity measurement carried out on split water sample collected from the same depths of suspended solids samples.
Sampler
3.2.10 A water sampler is required. It comprises a transparent PVC cylinder, with a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends. The sampler have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (for example, Kahlsico Water Sampler or an approved similar instrument).
Water Depth Detector
3.2.11 A portable, battery-operated echo sounder shall be used for the determination of water depth at each designated monitoring station. This unit can either be hand-held or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.
Salinity Measuring Equipment
3.2.12 A portable salinometer capable of measuring salinity in the range of 0 - 40 parts per thousand (ppt) provided for measuring salinity of the water at each monitoring location.
pH Measuring Equipment
3.2.13 The instrument consists of a potentiometer, a glass electrode, a reference electrode and a temperature-compensating device. It is readable to 0.1 pH in a range of 0 to 14. Standard buffer solutions of at least pH 7 and pH 10 used for calibration of the instrument before and after use. Details of the method should comply with American Public Health Association (APHA), 19th Edition 4500-HTB.
Sample Containers and Storage
3.2.14 Water samples for SS determination stored in high density polythene bottles with no preservative added, packed in ice (cooled to 4°C without being frozen) and delivered to the laboratory and analysed as soon as possible after collection. Sufficient volume of samples collected to achieve the detection limit.
3.2.15 All in-situ monitoring instruments checked, calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes checked with certified standard solutions before each use. Wet bulb calibration for a DO meter carried out before measurement at each monitoring location.
3.2.16 Sufficient stocks of spare parts shall be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.
3.2.17 Analysis of SS levels shall be carried out in a HOKLAS or another international accredited laboratory. Sufficient water samples (i.e. not less than 2 litres) collected at the monitoring stations for carrying out the laboratory determinations, with detection limit shown in Table 3.6. All samples assigned a unique code and accompanied by Chain of Custody (COC) sheets.
3.2.18 The SS determination work start within 24 hours after collection of the water samples. The analyses follow the standard methods according to Table 3.6 and as described in “American Public Health Association (APHA) Standard Methods for the Examination of Water and Wastewater”, 19th edition, unless otherwise specified.
Table 3.6 Analytical Methods to be applied to Water Quality Samples
Determinant |
Standard Method |
Detection Limit |
Suspended Solids (mg/L) |
APHA 2540 D |
2 mg/L |
3.2.19 For the purpose of QA/QC, all QA/QC results including blank, spike recovery, number of duplicate samples per batch, etc. reported in accordance with the requirement of HOKLAS or international accredited scheme. detection limits and accuracy submitted to EPD for approval prior to the commencement of monitoring programme. EPD may also request the laboratory to carry out analysis of known standards provided by EPD for quality assurance.
3.2.20 Additional duplicate samples may require by EPD for inter laboratory calibration. Remaining samples after analysis kept by the laboratory for 3 months in case repeat analysis is required. If in-house or non-standard methods are proposed, details of the method verification may also require submitting to EPD. In any circumstance, the sample testing has comprehensive quality assurance and quality control programmes. The laboratory prepares to demonstrate the programmes to EPD or his representatives when requested.
3.2.21 The monitoring station for water quality monitoring pertinent to the Project has been identified based on the approved EM&A Manual for HSKEPP of the Project. The location of the water quality monitoring stations is shown in Table 3.7 and shown in Figure 3.2.
Table 3.7 Locations of Water Quality Monitoring Stations
Monitoring Station No. |
Description |
Coordinates |
|
Easting |
Northing |
||
C1 |
Control Station at upstream location of construction site for stream water quality monitoring during construction phase |
816278 |
834038 |
M1 |
Impact station at downstream location of construction site for stream water quality monitoring during construction phase |
816571 |
833970 |
3.2.22 The schedule for water quality monitoring conducted in September 2024 is provided in Appendix E.
4.1.1 The Contractor has implemented environmental mitigation measures and requirements as stated in the EIA report, the EP and EM&A Manual. The implementation status of the environmental mitigation measures during the reporting period is summarized in Appendix C.
5.1.1 According to the approved EM&A manual, 1-hour TSP impact monitoring should be conducted at the monitoring stations when Project-related major construction activities being undertaken within a radius of 500m from the monitoring stations.
5.1.2 The dust monitoring results for 1-hour TSP are summarised in Table 5.1 and the monitoring data with the graphical plots are presented in Appendix F. The wind speed and wind direction data obtained from the Lau Fan Shan Automatic Wind Station operated by Hong Kong Observatory are presented in Appendix G.
Table 5.1 Summary of 1-hour TSP Monitoring Result in the Reporting Period
ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AM1 |
71.0 |
4 – 155 |
263.0 |
500 |
AM2 |
61.0 |
18 – 168 |
260.6 |
500 |
AM3 |
64.8 |
29 – 182 |
263.4 |
500 |
5.1.3 No Action and Limit Level exceedance were recorded for 1-hour TSP monitoring in the reporting month.
5.1.4 The event and action plan is annexed in Appendix H.
5.1.5 Major dust sources during the monitoring included construction dust, nearby traffic emission and other nearby construction sites.
5.2.1 According to the approved EM&A manual, water quality monitoring at designated locations are proposed to be carried out during the construction phase to monitor any sub-standard water discharge into the nearby water bodies from the HSKEPP.
5.2.2 The water quality monitoring results are summarized in Table 5.2. The monitoring data with graphical plots and their corresponding Action and Limit levels are provided in Appendix I.
Table 5.2 Summary of Water Quality Monitoring Results in the Reporting Period
Parameters |
Monitoring Station ID |
M1 |
|
Dissolved Oxygen (mg/L) |
4.26 – 6.44 |
Turbidity (NTU) (Depth-averaged) |
3.16 – 17.78 |
Suspended Solid (mg/L) (Depth-averaged) |
3 – 13 |
5.2.3 No Action and Limit Level exceedance were recorded for water quality monitoring in the reporting month.
5.2.4 The event and action plan is annexed in Appendix H.
5.3.1 C&D materials and wastes sorting were carried out on site. Receptacles were available for C&D wastes and general refuse collection.
5.3.2 As advised by the Contractor, no inert C&D materials were generated in the reporting month. No inert C&D materials were reused in other projects or in the Contract in the reporting month. No general refuse and yard waste was disposed of in the reporting month. No paper / cardboard packaging, plastic wastes and metals were generated and disposed in the reporting period. The waste flow table for different wastes in this reporting month is presented in Table 5.3 and the cumulative waste flow table is annexed in Appendix J.
Table 5.3 Quantities of Waste Generated and Disposal Location in the Reporting Period
Sep 2024 |
Quantities of Waste |
|||||||
Inert C&D Materials (in ‘000 kg) |
Chemical Waste (in ‘000 L) |
Non-inert C&D Materials |
||||||
Others, e.g. General Refuse (in ‘000 kg) |
Recycled Materials |
|||||||
Paper (in ‘000 kg) |
Plastics (in ‘000 kg) |
Metals (in ‘000 kg) |
Yard Waste (in ‘000 kg) |
|||||
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Disposal Locations |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
5.3.3 The Contractor is advised to properly maintain on site C&D materials and wastes collection, sorting and recording system and maximize reuse / recycle of C&D materials and wastes.
5.4.1 Site inspection was undertaken by the ET at least once every month during the construction period (i.e. 26 September 2024). Site inspection and implementation Schedule of Environmental Mitigation Measures is provided in Appendix C. The observations and recommendations made during the site inspections are presented in Table 6.1.
6.1.1 Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures for the Project. A summary of the mitigation measures implementation schedule is provided in Appendix C.
6.1.2 In the reporting month, 3 site inspections were carried out on 12, 16 and 26 September 2024. Joint inspections with the IEC, ER, the Contractor and the ET were conducted on 26 September 2024. No non-compliance was recorded during the site inspection. Details of observations recorded during the site inspections are presented in Table 6.1.
Table 6.1 Observation and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air Quality |
12 Sep 2024 |
The Contractor was reminded to install wheel washing facility at the site exit. (Reminder) |
-- |
26 Sep 2024 |
The Contractor is reminded to display to NRMM label for drill rig properly. (Reminder) |
-- |
|
Noise |
N. A. |
Nil |
Nil |
Water Quality |
N. A. |
Nil |
Nil |
Waste/ |
16 Sep 2024 |
It is observed that chemical containers were found placed without drip tray. The Contractor is advised to provide drip tray to all chemical containers on site. (Observation) |
Chemical containers have been placed with drip tray. |
26 Sep 2024 |
It is observed that missing drip trays for chemical container and generators. The Contractor shall provide drip trays for generators and chemical container. (Observation) |
Chemical container and generator have been put on drip trays. |
|
Landscape & Visual |
N. A. |
Nil |
Nil |
Permits/ |
N. A. |
Nil |
Nil |
6.1.3 All follow-up actions requested by Contractor's ET and IEC during the site inspection were undertaken as reported by the Contractor and confirmed in the following weekly site inspection conducted during the reporting period.
7.1.1 No Action and Limit Level exceedance was recorded for 1-hour TSP monitoring in reporting month.
7.1.2 No Action and Limit Level exceedance was recorded for water quality monitoring in reporting month.
7.1.3 Summary of Exceedance is provided in Table 7.1.
Table 7.1 Summary of Exceedance
Environmental Parameter |
No. of Exceedance This Month |
Exceedance due to Project Construction |
||
Action Level |
Limit Level |
|||
Air
Quality |
0 |
0 |
0 |
|
Water Quality |
Dissolved Oxygen |
0 |
0 |
0 |
Turbidity |
0 |
0 |
0 |
|
Suspended Solid |
0 |
0 |
0 |
|
Total |
0 |
0 |
0 |
7.2.1 No environmental non-compliance was recorded in the reporting month. Summary of Environmental Complaints, Summon and Successful Prosecution are provided in Table 7.2 and Appendix K respectively.
Table 7.2 Summary of Environmental Complaints, Summon and Successful Prosecution
|
Total No. Received in this Reporting Month |
Cumulative No. Received since Project Commencement |
Environmental Complaints |
0 |
0 |
Notification of Summons |
0 |
0 |
Successful Prosecutions |
0 |
0 |
8.1.1 The major construction works between October 2024 to December 2024 will be:
Table 8.1 Major Construction for the Next Three Month
Location |
Site Activities |
Contract No. DC/2023/15 Site Formation Works for Hung Shui Kiu Effluent Polishing Plant Phase 1 |
- Construction of Hoarding - Demolition Works - Ground Investigation Works - Environmental Site Investigation Works - Tree Felling Works |
8.2.1 Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, construction noise, water quality, waste management and landscape.
8.3.1 The tentative schedules for dust and water quality monitoring in October 2024 are provided in Appendix E.
9.1.1 No Action and Limit Level exceedance was recorded for 1-hour TSP monitoring in reporting month.
9.1.2 No Action and Limit Level exceedance was recorded for water quality monitoring in reporting month.
9.1.3 3 nos. of environmental site inspections were carried out in September 2024. Recommendations for environmental site improvement were given to the Contractor for the deficiencies identified during the site audit.
9.1.4 No environmental complaint, notification of summon and successful prosecution was received in the reporting month.
9.2.1 According to the environmental site inspections performed in the reporting month, the following recommendations were provided:
Air Quality Impact
· Provide proper dust suppression measures, such as wheel washing facility at the site exit.
· Ensure the NRMM label is displayed properly for equipment.
Noise Impact
· No specific observation was identified in the reporting month.
Water Quality Impact
· No specific observation was identified in the reporting month.
Chemical and Waste Management
· Provide sufficient no. of drip trays for equipment and chemical containers and ensure the trip drays are in good condition to prevent chemical spillage.
Landscape & Visual Impact
· No specific observation was identified in the reporting month.
Permits/licenses
· No specific observation was identified in the reporting month.